B&KBakırcı & Keskin
EN
TürkçeEnglishDeutschРусскийالعربية中文Français
Menu

Turkey–Poland CMR Delay Claims: Article 19, the 21-Day Notice and the Freight-Charge Cap

Turkey Poland CMR delay claim: a late road delivery between Türkiye and Poland is not compensated under the same rule as cargo loss or physical damage. CMR Article 19 defines delay; Article 23(5) requires proof of damage caused by delay and ordinarily caps compensation at the carriage charges; Article 30(3) bars delay compensation unless a written reservation is sent within twenty-one days from the time the goods were placed at the consignee’s disposal.

Short and clear answer

To recover for a Turkey–Poland CMR delay, prove three separate points: that delivery was delayed within Article 19, that the delay caused a financial loss, and that the Article 30(3) written reservation was sent in time. Article 23(5) ordinarily limits the delay compensation to the carriage charges even when the proved commercial loss is higher.

A production-line stoppage, missed retail promotion, storage charge or contractual penalty is not automatically recoverable merely because the truck arrived late. The claimant must establish causation and quantify the damage. If a special interest in delivery was properly declared under Article 26, additional proven damage may be claimed within the declared amount according to the Convention. Article 29 can affect the ordinary limitation framework only when its misconduct threshold is proved.

1. CMR applies to qualifying Turkey–Poland international road carriage

CMR Article 1 applies to a contract for carriage of goods by road for reward when the contractual place of taking over and place designated for delivery are in different countries and at least one is a Contracting State. Türkiye and Poland are CMR Contracting States. A load taken over in Bursa for delivery in Warsaw, or in Łódź for delivery in Mersin, therefore falls within the Convention when the other Article 1 conditions are present.

The route can cross several transit states without changing the core Article 1 test. What matters is the carriage contract’s taking-over and designated-delivery places. If several separate transport contracts exist, each should be identified rather than assuming that every domestic pre-carriage, international leg and last-mile movement is one CMR contract.

Delay liability belongs to the carrier under the qualifying contract. A freight forwarder that acted only as intermediary is not automatically the CMR carrier, while a forwarder that undertook the carriage obligation may have a different legal position. Preserve the accepted booking, quotation, freight invoice, CMR/e-CMR and subcontract documents.

2. Article 19 defines delay in two different ways

Article 19 states that delay in delivery occurs when the goods have not been delivered within the agreed time limit. If no time limit was agreed, delay exists when the actual duration of carriage, having regard to the circumstances and, for partial loads, the time required for making up a complete load in the normal way, exceeds the time that it would be reasonable to allow a diligent carrier.

This means the first question is contractual. If the accepted transport order states a fixed delivery date and time, compare actual delivery against that commitment. If it merely gives an estimate, collection window or expected transit time, determine whether it amounts to an agreed Article 19 time limit. The actual wording matters.

Where no binding delivery time was agreed, Article 19 does not permit an arbitrary assumption that every route must take a fixed number of hours. The test is the reasonable duration for a diligent carrier in the circumstances. Border procedures, mandatory driving and rest periods, ferry schedules where relevant, weather and route conditions may be factual elements, but they do not automatically excuse delay under Article 17.

A carrier’s internal ETA is useful evidence but does not necessarily alter the contractual time limit. Preserve all versions of booking confirmations and ETA messages so the parties’ contractual position is not reconstructed after the loss.

Turkey–Poland late-delivery dispute? Build a minute-by-minute chronology from collection to consignee disposal and preserve the written reservation. Send the transport file to our Mersin office in English.

3. A delay claim is won or lost on the chronology

Record the agreed collection time, actual collection, border arrivals and departures, customs-document requests, driver rest stops, transshipment events, vehicle faults, terminal waits, delivery appointment, actual arrival and the time the goods were placed at the consignee’s disposal. GPS and telematics should be matched to messages and documents rather than read in isolation.

If the claimant alleges a missed delivery slot, preserve the consignee’s slot confirmation and proof that later delivery was refused or rescheduled. A truck arriving at a gate can differ from legal delivery or from the moment the goods are at the consignee’s disposal. Article 30(3) uses the latter concept for the twenty-one-day reservation period.

Where the carrier says the sender caused the delay, identify the exact event: late loading, missing customs document, incorrect weight, incomplete transit information or changed instructions. Article 11 allocates responsibilities for customs and other formalities, while Articles 12–16 address instructions and obstacles. A generic statement that “customs caused the delay” is too vague to establish who bore the relevant responsibility.

Where a vehicle fault is blamed, Article 17(3) is important: the carrier is not relieved by the defective condition of the vehicle used for carriage or by the fault of the person from whom it hired the vehicle. Repair records and substitution arrangements should be preserved.

4. Border or customs delay is not automatically a CMR defence

Article 17(2) allows relief where delay was caused by circumstances the carrier could not avoid and whose consequences it was unable to prevent, as well as the other causes stated by the Convention. The carrier bears the proof burden for Article 17(2) circumstances under Article 18(1).

A queue at a border can therefore be relevant but is not a legal conclusion. Establish when the vehicle joined the queue, what caused the hold, whether documents were complete, whether the carrier followed the instructed customs procedure, whether another route or timely action was available, and how much of the total delay is attributable to that event.

Article 11 is particularly important when required customs documents or information are missing or irregular. The sender must place the necessary documents and information at the carrier’s disposal, and the Convention allocates liability for their absence, inadequacy or irregularity subject to carrier fault. The carrier, in turn, is responsible for loss or incorrect use of documents entrusted to it within Article 11’s terms.

If the sender changes the destination or gives new instructions during transit, preserve the instruction and the carrier’s response. Articles 12–16 govern rights of disposal, impediments and related expenses. Delay caused by a later valid instruction should not be analysed as if the original delivery timetable remained untouched.

Do not label every border wait “force majeure.” Identify the responsible document, instruction, queue event and preventability issue under Articles 11, 17 and 18.

5. Article 23(5) requires proof that the delay caused financial damage

Article 23(5) provides that, where the claimant proves that damage has resulted from delay, the carrier must pay compensation not exceeding the carriage charges, subject to the Convention’s other provisions. The late delivery itself does not establish the amount of damage.

For a factory shipment, prove the production plan, inventory position, missing component, actual stoppage period and additional expense. For retail goods, prove the relevant promotion, delivery obligation and actual reduction or additional cost attributable to the delay. For perishable goods, distinguish deterioration caused by temperature or inherent condition from purely economic delay damage; different CMR compensation provisions may apply.

Contractual penalties between seller and buyer require careful analysis. A penalty paid under a sales agreement does not automatically become the carrier’s CMR liability. The claimant must establish causation, legal entitlement and the Convention’s compensation framework. The carrier may also challenge whether the underlying payment was actually due.

Maintain a loss schedule supported by invoices, payroll or production records, storage invoices, substitute-transport costs and credits received. Avoid presenting lost revenue as if it were automatically lost profit. The CMR claim should identify the actual economic detriment.

6. The ordinary delay ceiling is the carriage charges, not 8.33 SDR per kilogram

The 8.33 SDR-per-kilogram rule under the 1978 Protocol is associated with the Article 23(3) ceiling for loss of goods. Delay has a separate ordinary ceiling in Article 23(5): the compensation for proved delay damage must not exceed the carriage charges.

This distinction is commercially important. A low freight charge can cap a much larger production-line or retail loss. Claimants should therefore check whether the carriage contract contains a valid Article 26 special-interest declaration and whether Article 29 is pleaded on supported facts. Neither exception should be assumed.

Identify what constitutes the carriage charges for the relevant contract. The freight invoice may include separate customs brokerage, warehousing, ferry, fuel surcharge or other amounts. The Article 23(5) calculation should be tied to the contract and the charges legally characterized as carriage charges.

Physical cargo damage occurring during a late journey is not converted into delay damage simply because the shipment was also late. Article 25 may govern physical damage, while Article 23(5) governs damage resulting from delay. Separate each head of claim.

Delay is not an 8.33 SDR/kg claim. Start with Article 23(5), the proved loss and the carriage charges, then check Article 26 and Article 29 separately.

7. Article 26 can matter where late delivery carries exceptional commercial risk

Article 26 permits the sender, against payment of a surcharge agreed with the carrier, to fix the amount of a special interest in delivery in case of loss, damage or exceeding the agreed time limit. If a special interest has been declared, compensation for additional loss or damage proved may be claimed, up to the declared amount, within the Convention’s terms.

A transport order saying “urgent,” “JIT” or “production critical” is not automatically an Article 26 declaration. The file should show the agreed surcharge and the declared amount in the carriage documentation. Internal supplier scorecards and buyer penalties have different purposes.

For regular Turkey–Poland automotive or industrial routes, the parties can therefore allocate unusual delay exposure at the contracting stage rather than trying to reconstruct it after a missed delivery. Whether that occurred in the actual shipment must be proved from the accepted contract.

Article 29 remains separate. It removes the carrier’s ability to rely on Convention exclusions and limits only on its wilful-misconduct or equivalent-default threshold under the law of the court or tribunal seized. Ordinary delay, poor planning or a single traffic incident should not automatically be labelled Article 29 misconduct.

8. Article 30(3) creates a strict twenty-one-day written reservation rule for delay

Article 30(3) states that no compensation is payable for delay in delivery unless a written reservation has been sent to the carrier within twenty-one days from the time the goods were placed at the consignee’s disposal. The triggering day is not included in the period under Article 30(4).

This is different from the seven-day rule for non-apparent physical loss or damage. A claimant should not use a concealed-damage template and assume that it protects a delay claim. The reservation should clearly identify the late delivery and preserve evidence of sending and receipt.

The wording should be written, not a phone call. Email can provide a practical written record when authenticity, sender, recipient and timing are preserved. Keep the original message, headers where available and attachments. If the transport terms prescribe a claim portal, also preserve the portal submission receipt.

The reservation does not need to contain the final quantified damages if those are not yet known, but it should unambiguously reserve the delay claim. A detailed quantified claim can follow with supporting evidence.

Twenty-one days is not a negotiation target. Send a clear written delay reservation within Article 30(3) and preserve proof of transmission.

9. Article 32 limitation and Article 31 jurisdiction still apply

Article 32 provides an ordinary one-year limitation period and a three-year period for the wilful-misconduct/equivalent-default situation described by the Convention. For delay, the period begins from the date of delivery. The day from which the period begins is not included.

A written claim can suspend the limitation period under Article 32(2) until the carrier rejects the claim in writing and returns documents attached to it. Repeated claims do not create repeated suspension under the Convention. The Article 30(3) reservation and Article 32(2) written claim should therefore be tracked as separate procedural events.

Article 31 identifies the permitted international forums. Depending on the defendant, place of taking over, designated delivery place and any valid agreed Contracting-State forum, a Turkey–Poland dispute may be brought in Türkiye, Poland or another treaty-permitted forum. The exact Turkish court, where Türkiye is available, is determined under Turkish procedural rules.

Frequently asked questions

What counts as delay under CMR?

Article 19 uses the agreed delivery time where one exists; otherwise it uses the reasonable time allowed to a diligent carrier in the circumstances.

Is every border queue a carrier defence?

No. The carrier must prove a Convention ground of relief and the relevant causation under Articles 17 and 18.

Can I recover a factory shutdown loss in full?

Article 23(5) requires proof of delay damage and ordinarily caps compensation at the carriage charges, subject to applicable Convention exceptions.

Is the delay cap 8.33 SDR per kilogram?

No. The ordinary delay cap is the carriage charges under Article 23(5).

How long do I have to reserve a delay claim?

Article 30(3) requires a written reservation within twenty-one days from the time the goods were placed at the consignee’s disposal.

Can a special interest in delivery increase recovery?

Article 26 can permit additional proved damage up to the declared amount when its contractual conditions are satisfied.

Does an “urgent” booking automatically count as Article 26?

No. Check for the agreed surcharge and declared special-interest amount required by the Convention.

When does the action limitation period start for delay?

Under Article 32 it starts from the date of delivery, with the triggering day excluded from the calculation.

Official sources

UNIDROIT — CMR Convention, especially Articles 11, 17–19, 23, 26, 30–32; United Nations Treaty Collection — 1978 Protocol to CMR.

Istanbul and Mersin offices and Turkey-wide coordination

Istanbul: Maslak Ahi Evran Caddesi, Polaris Plaza No:21, Kat:9, 34475 Sarıyer/İstanbul, Türkiye
Mersin: İhsaniye Mahallesi, 4903. Sokak, Profit İş Merkezi No:23, Floor 3, Office 14, 33070 Akdeniz/Mersin, Türkiye

Our physical offices are in Istanbul (Maslak/Sarıyer, Polaris Plaza) and Mersin (Akdeniz, Profit İş Merkezi). Turkey-facing international road-freight claims are coordinated from these offices subject to jurisdiction and mandate.

Contact in English · +90 552 224 43 66 · Directions

Istanbul Office – Polaris Plaza, Maslak / Sarıyer

Bakırcı & Keskin Hukuk Bürosu

Maslak Ahi Evran Caddesi, Polaris Plaza No:21, Kat:9, 34475 Sarıyer/İstanbul

Our physical offices in Istanbul and Mersin coordinate matters throughout Turkey, subject to jurisdiction and the local steps required for each case. Please specify your preferred office when arranging an in-person appointment.

Open the Istanbul office on Google Maps · Contact and appointments

Contact regarding a legal matter

In your first message, you may briefly state the subject, your country or city, and any relevant notification or recent procedural date. Please do not send identity numbers, medical data, or personal documents. Messaging alone does not constitute legal advice or create a lawyer–client relationship.

CallContact information

Discover more from Bakırcı & Keskin Hukuk Bürosu

Subscribe to get the latest posts sent to your email.

    ISTANBUL · MERSIN · ONLINE

    Request a legal consultation

    Briefly describe your matter and choose an office or an online meeting, if you have a preference.

    Fields marked * are required.




    Message length0 / 1000

    Characters remaining: 1000Spaces are included.You’re approaching the limit.You’ve reached the 1,000-character limit.

    Please do not include identity numbers, banking details or sensitive documents. Privacy notice (Turkish)

    An initial enquiry does not establish an attorney–client relationship or suspend legal deadlines. Please call us for urgent matters.

    Ask a Question About This Article

    Real questions may be published anonymously after review. Do not share names, contact details, ID or case numbers, or personal information. This is not legal advice.

    Privacy policy

    Telefon WhatsApp